Show all dependencies for a task

Cotters
Tera Contributor

I want to be able to see all dependencies driving a task, the Gantt chart is impossible to use for this because it is not possible to see whether there is more than one dependency.

I had hoped there would be something on the task details page that shows this, but I can't find it.

I hate referring back to MS Project, but to be honest, the task info shows this very well.

2 REPLIES 2

Brad Bowman
Mega Patron

I had missed this too until I added the Planned Task Relationship -> Predecessor and Planned Task Relationship -> Successor related lists to the Project Task form.  Not sure why this isn't out of box.

 

Thanks, I don't think I have access to do this, but I'll ask someone who has.