SPM - Financials baselines comparison

Tommaso2
Tera Expert

Hi all,

 

When I compare 2 financials baselines in the Project Workspace, I can only compare (see the attachment):

- Forecast

- Planned

 

I read that I should be able to compare many other financials, e.g. budget.

Maybe something has to be configured?

 

 

Many thanks

1 ACCEPTED SOLUTION

Vinay3
ServiceNow Employee

Hi @Tommaso2 , compare baselines in the new project workspace only supports comparing differences between forecasts of costs between two points in time.

Ability to compare budget is not yet supported.

View solution in original post

3 REPLIES 3

Vinay3
ServiceNow Employee

Hi @Tommaso2 , compare baselines in the new project workspace only supports comparing differences between forecasts of costs between two points in time.

Ability to compare budget is not yet supported.

Hi, Vinay.

We have a customer asking for a comparison of budgets along the baselines.

It's been a while since your answer. Any progress on this? It seems strange that this functionality is not there.

 

Daniel

Alpa82
Mega Sage

I would have the same question, since the budgets changes are captured in the baseline, one would expect to be able to see them also in the baseline comparison on the project financials.