Status report
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 hours ago
Is there any way to add data from financials tab to project workspace. Currenlty there are limited available fields in the project table which can be selected from dynamic content, i want to add Budget(capex & Opex), planned cost (capex and opex ), EAC(capex opex ), Eac vs budget Varience(capex opex) and actuals.
I have budget in project but not seperated as capex and opex, i have planned cost seperated, EAC is there but varience in EAC and budget varience is not there in project table but available in workspace.
0 REPLIES 0