Timecards can only be submitted and/or approved against projects in a work in progress state and resource assignment is in an approved status.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hi @prash4 ,
Thanks for connecting with community.
Can you explain what is your query?
Have a great day!
Thank You!
Namita Mishra
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago - last edited 3 weeks ago
Requirement:
Timecards should only be submitted and approved only when both conditions are met:
1. Project State Validation
The project associated with the timecard must be in Work in Progress (WIP) state.
If the project is in any other state (Planning, Proposed, On Hold, Closed, etc.), the system should:
Block submission
Block approval
Display an error message to the user
2. Resource Assignment Validation
The user submitting the timecard must have an Approved Resource Assignment for the project.
If no approved resource assignment exists for the user and project, the system should:
Block submission
Block approval
Display an error message