When a project gets created and a project task has no predecessors and has "Start on specific date" does the project automatically starts and changes to work in progress when the date hits? I don't recall that it should, but we have some of our users stating that it used too or that it did. Is there anyway to verify from you guys?
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-04-2016 11:55 AM
Hello Tou. Project Tasks with Start On time constraint don't auto-start. However, if that date is in the past, and the project is started, all such tasks will get converted to Start ASAP. And if they are first level tasks (with the project as their parent), they will become Work In Progress.
Hope this helps.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-04-2016 12:04 PM
Thank you. The only thing that strayed me away was Geneva's new feature with project (if it did impact).