Problem Task reporting - How to track records that had changed due dates

Prem Singh
Tera Contributor

Hello team,

 

I am doing management report to track how many problem tasks that had due dates changed. In the reporting of problem task as table, i set the condition filters for those tasks that are not closed and used the condition of setting the due date is different from due date (I know , it doesnt make sense) - see the attached screenshot. However not able to do so.. I dont think the report detects any changes? Any help pls.

 

2 REPLIES 2

Aman Kumar S
Kilo Patron

Hi @Prem Singh ,

You can make use of Metric > Definition, and create a new one as below for your reporting purpose.

Capture101.PNG

Best Regards
Aman Kumar

Prem Singh
Tera Contributor

Thank you Aman , as i dont have the access to add the new entry, would raise a request with our SNOW admin team to create it.