We will be scheduling an upgrade for PROD moving from Vancouver to Washington for this Sunday starting at 7pm EST.

 

Is it true that the upgrade can start anytime up to 4 hours after that?  If so, are there any exceptions to that?

1 REPLY 1

Mark Manders
Mega Patron

Check the 'Check distribution for possible upgrade' sys_trigger (scheduled job). OOB it runs once every hour to see if there is a new version for your instance. If so, it starts. So if the job runs at 1 minute before the hour, and your upgrade starts at the hour, it will take 59 minutes for the check and only then starts the upgrade.

If your job runs every 4 hours, it can indeed take 4 hours, but that's not the OOB setting. 


Please mark any helpful or correct solutions as such. That helps others find their solutions.