Migrate resource plans and cost plans for projects and demands

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 2분
  • Migrate resource plans and cost plans of your projects or demands to resource assignments and attribute-bases cost plans and work on the resource allocations and project financials using Project Workspace.

    시작하기 전에

    프로시저

    1. Use one of the following options to open a project or a demand.
      • To open a project, navigate to All > Project > Projects > All and open a project.
      • Too open a demand, navigate to All > Demand > Demands > All and open a demand.
    2. Select the Migrate resource plans related link.
      주:
      This selection triggers the migration of resource plans and cost plans simultaneously.
    3. In the Migrate Resource Plans confirmation window, select OK.

    결과

    Resource plans are migrated to resource assignments, cost plans are migrated to attribute-based cost plans. Refresh the project page to view the resource assignments in Resource assignments related list.

    다음에 수행할 작업

    Create resource assignments to manage resource efforts.