Request Extension form

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Use the Request Extension form to request extension of an allocated resource plan.

    표 1. Request Extension form
    Field Description
    Extend until Date until which you want to extend the resource plan and request for resources.
    Request type Type of request. Options include: FTE, Person Days, or Hours.
    FTE or Person days or Hours Number of units to request resources.

    The field appears when you select one of the options in the Request type field. Based on the selected request type, specify the unit.

    For more information, see Request type.

    Notes Other correspondence and information about the resource plan that the project manager wants to communicate with the resource manager.