Configure a custom risk rank and risk value

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 2분
  • Configure custom risk ranks and value scores to rate the impact and probability factors for a risk.

    시작하기 전에

    Role required: pps_admin

    이 태스크 정보

    Use the Risk Value Lookup module to set up the risk rank and risk value for a specific combination of risk impact and probability. The system uses these values to determine the degree of risk (Absolute, High, Medium, and Low) based on the impact and probability factors of a risk.

    The value in the Probability field is multiplied by the value of the Impact field to generate the values for the Risk rank and corresponding Risk value in the Create New Risk form.

    By default, you can use the following impact, value, and probability scores for a risk to create a risk rank and risk value score:

    • Absolute
    • Low
    • Medium or Moderate
    • High
    For example, a risk might have high probability and medium impact but you might want to consider it as an overall low risk for the demand. In that case, you would configure the Risk Value Matcher form with the following values:
    • Impact = 2 Medium
    • Risk Rank Color = Green
    • Probability = High
    • Probability Number = 1
    • Risk Value = 3 Low
    In this case, the calculated risk rank and value are as follows:
    • Calculated risk rank = 2
    • Calculated risk value = 2

    프로시저

    1. Navigate to All > Project Administration > Settings > Risk Value Lookup.
    2. Select New.
    3. On the risk value lookup form, fill in the fields.
      For a description of the field names, see Risk value lookup form.
    4. Select Submit.