Pre-date a project task

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 2분
  • Move the planned start date of a task prior to the planned start date of a project. Adding a pre-dated task allows you to accommodate tasks which need to start before the planned start date of a project.

    시작하기 전에

    You should have created or added project tasks to your project.

    Role required: it_project_manager

    이 태스크 정보

    Before pre-dating a project task, note the following conditions:
    • The property project.rollup_project_start_date should be set to true.
    • Pre-dating a task's planned start date also moves the project's planned start date.
    • The start date of a child task cannot be moved prior to the parent task's start date. For example, if a parent task with Start no earlier than constraint starts on 20th and the child task starts on 30th, the start date of the child task can only be moved up to 20th.

    프로시저

    1. Navigate to All > Project > Projects > All.
    2. Select the project from the list.
    3. On the Project form, update the planned start date for a project task using either of the following options.
      OptionSteps
      From the Project Task form
      1. In the Project Tasks related list, select the project task which you want to pre-date.
      2. On the Project Task form, select the Dates tab and update the Planned start date for the task.
      From the Planning Console
      1. On the Project form, select the Planning Console related link.
      2. In the Planning Console, update the start date of the project task under the Planned start date column.
    4. In the Move date dialog box, select OK.