Recalculate resource costs form
Use the recalculate resource costs form to make sure that the resource assignment costs are up to date.
| Field | Description |
|---|---|
| Start date | Start date of the time period for which the costs are recalculated. By default, the field shows the current date. |
| End date | End date of the time period for which the costs are recalculated. By default, the field shows the due date of the demand. If the due date isn’t specified for the demand, the field is empty. |
| Planned costs for Requested Resource plans | Option for recalculating the planned cost of Requested resource plans. |
| Confirmed/Allocated costs for Confirmed/Allocated resource plans | Option for recalculating the confirmed or allocated cost of confirmed or allocated resource plans. |
| Planned costs for Confirmed/Allocated resource plans | Option for including the planned cost of a confirmed or allocated plan. The option is enabled if the Confirmed/Allocated costs for Confirmed/Allocated resource plans option is selected. By default, the option isn’t selected. |