Create a project task in the project workbench

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Create a project task for a waterfall phase.

    시작하기 전에

    Role required: it_project_manager

    이 태스크 정보

    While creating a project task in the project workbench, the time constraint type is defaulted based on the project type.
    • For a manual project, the default constraint is Start On and cannot be changed.
    • For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
    • When the constraint is Start ASAP, the Planned start date is disabled.
    • When you create an agile phase and associate a sprint, the start date of the task is set from the sprint start date and the constraint becomes Start On automatically.

    프로시저

    1. Select a waterfall phase in the project workbench timeline.
    2. Select New in the detail view.
    3. Fill out the Project Task form.
    4. Select Submit.