Enable attribute-based resource assignments
Enable the property to work on attribute-based resource assignments to request efforts for your planning items.
시작하기 전에
- If a project, demand, or a task has at least one attribute-based resource plan, Resource plans related list is hidden.
- If a project, demand, or a task has at least one resource plan without any attribute-based resource assignments, Resource plans related list is visible.
- If a project, demand, or a task has no resource plans and the sn_pw.enable_resource_planning property is enabled, Resource assignments related list is available, else, Resource plans related list will be available.
- If a project, demand, or a task has at least one attribute-based resource assignment, New and Manage options are hidden for Resource plans.
- If a project, demand, or a task has at least one resource plan without any attribute-based resource assignments, New and Manage options are available for Resource plans.
- If a project, demand, or a task has no resource plans and the sn_pw.enable_resource_planning property is enabled, New and Manage options are hidden for Resource plans, else, they will be available.
Role required: admin
프로시저
- Navigate to .
- Filter the name field to locate and open sn_pw.enable_resource_planning.
- Change the scope of the instance to Project Workspace.
- Clear the Value field and enter true.
- Select Update.