Legacy- Tracking view in portfolio workbench
Once the financial planning is complete, the Track Portfolio option in portfolio workbench is enabled. You can track the progress of demands and projects, and monitor the status of cost, resource, schedule, and scope for the selected fiscal period for the portfolio.
주:
The content in this topic is applicable for customers upgrading from a previous release to
Australia. If you are a new customer, see Scenario Planning for PPM.
The portfolio workbench comprises the following components in tracking view:
On the Timeline View tab, you can:
- configure the colors of the portfolio items in the Gantt chart with Dashboard Configuration settings.
- select the zoom level in the Gantt chart calender to Auto Fit. The Gantt view fits in one page to view entire timeline without using the scrollbar.
- review the external dependencies between projects in a portfolio.
주:
The admin can customize which columns appear in the column filter list (
) in the timeline view.
You can:
- click the name of a project on the tab to open the latest status report created for the project.
- point to a status indicator for a project KPI to view the comments entered for the KPI for that project.
주:
An expense line can be created manually for a project when a
specific expense is incurred. For example, if hardware is procured for a project, an expense
line can be created for the amount spent on procuring the hardware. If you receive an item using
ServiceNow
Procurement, an expense line is created
automatically. For resource hours, the expense lines are created automatically when the time
cards for the project are approved.
The display settings for the chart can be modified
by selecting any of the following from the choice list:
- Capex: Displays the cost chart for capital expense only.
- Opex: Displays the cost chart for operating expense only.
- All: Displays the cost chart for both capital and operating expenses.
Resource (Allocated vs. Actual): The chart displays the actual resource time spent on all project tasks versus the resource hours allocated to execute the selected projects and demands in the portfolio. The actual time spent is taken from processed time cards for the projects.
- Risks: Displays risks concerning all the selected demands and projects in portfolio and their probability. This information is populated from the risks that are part of demands and projects associated with the portfolio.
- Issues: Displays all issues across all selected projects in the portfolio and their priority. This information is populated from the issues that are reported for the projects in a portfolio.
- Changes: Displays all project change requests across all selected projects in the portfolio and their priority. This information is populated from the change requests created for the projects in a portfolio.