Project and project task states

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • In the base system, the states in project and project task inherit the states in Task table.

    The states are grouped into different categories as shown below:
    State Label Category
    -5 Pending Pending
    1 Open Open
    2 Work in Progress Work in Progress
    3 Closed Complete Closed
    4 Closed Incomplete Closed
    7 Closed Skipped Closed

    The category information for the states is declared in dictionary override of State column in Planned task (planned_task) table in Attributes field. Planned task is the parent table for project and project task tables.

    The start and end dates are displayed based on the project or task status:
    • Pending/Open: Planned start date is displayed.
    • Open/Work in Progress: Actual start date is displayed.
    • Closed: Actual end date is displayed.