Export project tasks

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • The task being exported must be associated with a project that uses either the Project Management Schedule or the Default MS Project schedule.

    시작하기 전에

    Role required: it_project_manager

    프로시저

    1. Navigate to Project > Projects > All.
    2. Open the project.
    3. Scroll to the Project Tasks related list and select a task number to open the Project Task form.
    4. Right-click the form header and select Export Task to MS Project from the context menu.

      The task is exported to a folder on your system.

    5. Open Microsoft Project to import the exported project task files.
      Refer to Microsoft product documentation for instructions.