Update the dependency details for tasks from Project Workspace

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Update the details of the dependency including its type and lag time from Project Workspace.

    시작하기 전에

    Role required: it_project_manager

    프로시저

    1. Open a project from the home page of Project Workspace.
      For information, see Access the new Project Workspace.
    2. Open the dependency side panel in one of the two ways.
      OptionAction
      From the data grid From the dependency column, select the dependency of the task.
      From the timeline view Select the dependency line.
    3. Edit the fields.
    4. Select Update.