Enable attribute-based resource assignments

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 2분
  • Enable the property to work on attribute-based resource assignments to request efforts for your planning items.

    시작하기 전에

    • If a project, demand, or a task has at least one attribute-based resource plan, Resource plans related list is hidden.
    • If a project, demand, or a task has at least one resource plan without any attribute-based resource assignments, Resource plans related list is visible.
    • If a project, demand, or a task has no resource plans and the sn_pw.enable_resource_planning property is enabled, Resource assignments related list is available, else, Resource plans related list will be available.
    • If a project, demand, or a task has at least one attribute-based resource assignment, New and Manage options are hidden for Resource plans.
    • If a project, demand, or a task has at least one resource plan without any attribute-based resource assignments, New and Manage options are available for Resource plans.
    • If a project, demand, or a task has no resource plans and the sn_pw.enable_resource_planning property is enabled, New and Manage options are hidden for Resource plans, else, they will be available.

    Role required: admin

    프로시저

    1. Navigate to All > System Properties > All.
    2. Filter the name field to locate and open sn_pw.enable_resource_planning.
    3. Change the scope of the instance to Project Workspace.
    4. Clear the Value field and enter true.
    5. Select Update.