Get a first look at what's coming. The Developer Passport Australia Release Preview kicks off March 12. Dive in! 

Change management

vishalrshin
Tera Contributor

Technical team have implemented change through Normal change process to resolve incidents. Change been suggested by a vendor . After implementing incidents didn't resolve. Would this be considered as unsuccessful change ?

1 REPLY 1

Najmuddin Mohd
Mega Sage

HI @vishalrshin ,

It depends. 
The change given by the vendor is actually the solution to the Incidents ?
Or the change was not implemented in the proper way by which Incidents didn't resolve.

I believe it as a Unsuccessful change, because it was meant to resolve the Incidents which didn't.

Hope this helps.
Regards,
Najmuddin.