We're reclaiming inactive PDIs to keep them available for active builders. Learn what's changing, who's affected, and how to protect your work. Read More

Change management

vishalrshin
Tera Contributor

Technical team have implemented change through Normal change process to resolve incidents. Change been suggested by a vendor . After implementing incidents didn't resolve. Would this be considered as unsuccessful change ?

1 REPLY 1

Najmuddin Mohd
Giga Sage

HI @vishalrshin ,

It depends. 
The change given by the vendor is actually the solution to the Incidents ?
Or the change was not implemented in the proper way by which Incidents didn't resolve.

I believe it as a Unsuccessful change, because it was meant to resolve the Incidents which didn't.

Hope this helps.
Regards,