Technical team have implemented change through Normal change process to resolve incidents. Change been suggested by a vendor . After implementing incidents didn't resolve. Would this be considered as unsuccessful change ?
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎09-18-2024 10:46 AM
HI @vishalrshin ,
It depends.
The change given by the vendor is actually the solution to the Incidents ?
Or the change was not implemented in the proper way by which Incidents didn't resolve.
I believe it as a Unsuccessful change, because it was meant to resolve the Incidents which didn't.
Hope this helps.