Recalculate Estimate at Completion and Estimate to Complete in SPM

MohitC600613157
Tera Contributor

Hi Community,

In an SPM implementation, our client wants Estimate to Complete(ETC) and Estimate at Completion(EAC) to be recalculated based on Planned Value only up to the 15th of the next month because they received the Actuals by mid of next month, but they do not want to modify the standard fiscal periods.

Has anyone implemented something similar?

Looking for guidance on:

  • Whether any OOTB capability supports this.
  • Recommended customization approach (if required).
  • Any known impacts to project financials or EV calculations.

Thanks for your inputs!

0 REPLIES 0