The requirement is : When closing the change task and going back to the change request form , close code and close notes on change task should carry the data to change request.
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-28-2017 03:17 PM
UI policy hiding/showing them? We made them mandatory on the change task when the State changes to Closed Complete.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-28-2017 03:05 PM
I recently did this on a Helsinki instance by adding the Change Task close code & close notes and when the task closed, it copied them to the Change Request. Just had to make sure the choices & values were the same between Change Task & Change Request.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-28-2017 03:13 PM
Not sure why when i close the change task , and then when i go back to check it , the close notes and close codes are not showing on the task. Although on the page lay out I have selected them to be shown!

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-28-2017 03:17 PM
UI policy hiding/showing them? We made them mandatory on the change task when the State changes to Closed Complete.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-28-2017 03:26 PM
Correct! thx