We moved to Flow, designer, last month and are kinda new to this. Need help, please!
Here is the issue.
When a task is closed skipped it does not update the RITM and REQ. It updates only when the task is close complete. How to I update RITM and REQ when sctasks are one of "Close complete/ Close incomplete/ Close skipped.
1 REPLY 1

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-24-2023 12:18 PM
You need to add Stages to your Flow. https://docs.servicenow.com/bundle/utah-build-workflows/page/administer/flow-designer/task/add-stage...
When you set the stage, a baseline business rule will close the RITM. When the RITM closes, the REQ will close.