Convert to Milestone in Project Management

Cirrus
Kilo Sage

Hi, 

Can anyone advise where Convert to Milestone is configured in both planning console and project workspace as they dont appear to be standard ui actions. 

 

Thanks

 

 

1 REPLY 1

M Iftikhar
Giga Sage

@Cirrus ,

Based on documentation, I think configuration is still from the backend, as when you change the duration value in the project task record to 0, it is converted to a milestone and appears as a diamond icon in the workspace Gantt chart. 

MIftikhar_0-1760532220836.png

 

 

Thanks & Regards,
Muhammad Iftikhar

If my response helped, please mark it as the accepted solution so others can benefit as well.