Hi,
Can anyone advise where Convert to Milestone is configured in both planning console and project workspace as they dont appear to be standard ui actions.
Thanks
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
9 hours ago
@Cirrus ,
Based on documentation, I think configuration is still from the backend, as when you change the duration value in the project task record to 0, it is converted to a milestone and appears as a diamond icon in the workspace Gantt chart.
Thanks & Regards,
Muhammad Iftikhar
Muhammad Iftikhar
If my response helped, please mark it as the accepted solution so others can benefit as well.