Can anyone advise where Convert to Milestone is configured in both planning console and project workspace as they dont appear to be standard ui actions. 

 

Thanks

 

 

1 REPLY 1

M Iftikhar
Tera Sage

@Cirrus ,

Based on documentation, I think configuration is still from the backend, as when you change the duration value in the project task record to 0, it is converted to a milestone and appears as a diamond icon in the workspace Gantt chart. 