Flow designer

-ooo-
Tera Contributor

Hello Team,

 

I developed one flow designer where i have added wait condition for after creation of task to check task is closed complete ,or not now this condition is satisfied . as per below screenshot.

 

ooo_0-1749482598445.png

 

after completed of first wait condition this flow needs to be ended . without using if , else we need to do . 

please advise. 

11 REPLIES 11

@-ooo- 

it should work fine

Did you publish the flow and test again?

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
Certified Technical Architect  ||  9x ServiceNow MVP  ||  ServiceNow Community Leader

-ooo-
Tera Contributor

@MY question in first screenshot you can see the first task is closed complete . also followed by completed RITM and req as well still it moves to next condition  in waiting state . flow needs to stop once first condition satisfied . instead moving waiting 

YaswanthKurre
Giga Guru

Hi @-ooo- ,

 

after you saved with wait to true - did you publish the flow, try publishing it.

 

Thanks,

yaswanth

-ooo-
Tera Contributor

yes already i tried this. here we need to create three conditions first one close completed then update RITM and req . if this is not satisfied then go for second like closed incomplete and then third closed skipped . in our case first satisfied then it should be stop der only . rather it moves to next waiting state . 

-ooo-
Tera Contributor

this is the first wait condition, and it satisfied then needs to stop after updating the records on RITM and Req only 

 

ooo_0-1749488890447.png