- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎05-03-2024 12:24 AM
Hello Everyone, I am not seeing the "Scheduled start" and "Scheduled end" in the drop down to filer the CTASK on the list view , but both the Scheduled start date, Scheduled end date are available on the CTASK form, could someone help me with the solution
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎05-03-2024 01:45 AM
Those aren't OOB CTASK fields. Are they dotwalked fields from the ChangeRequest table? In that case you need to add them via dotwalking.
Please mark any helpful or correct solutions as such. That helps others find their solutions.
Mark
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎05-03-2024 01:35 AM
Is these OOTB ? Bcz i cant see in my PDI
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎05-03-2024 01:45 AM
Those aren't OOB CTASK fields. Are they dotwalked fields from the ChangeRequest table? In that case you need to add them via dotwalking.
Please mark any helpful or correct solutions as such. That helps others find their solutions.
Mark
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎05-03-2024 01:58 AM
Hi @Chiranjeevi K ,
can you please share the screenshot of "Dictionary info" those two fields by right clicking on the field and show "Scheduled start date" and show "Scheduled end date" ?
Thank you.
Regards,