In a scoped application inherited from task, want to change the Label on Assigned To.

David Yearsley
Tera Expert

Starting a Scoped Application and inheriting from Task. I would like to change the label for the Assigned to field and the parent field. When you right click on the table and select label it shows the form to change the label for the current table, but it is grayed out and say this has to be done in the global app, not the scoped app. Is there another way to relabel a task field in a scoped app?

 

Thanks

1 ACCEPTED SOLUTION

David Yearsley
Tera Expert

You have to create a new label. In a scoped app you can create new labels. The base record cannot be changed.

View solution in original post

2 REPLIES 2

David Yearsley
Tera Expert

You have to create a new label. In a scoped app you can create new labels. The base record cannot be changed.