Planned Start Date Validation

ktjstn
Kilo Expert

I want to make a Planned Start Date Validation wherein a pop-up message will appear if the selected Planned Start Date is more than 7 days to the current date.

 

Thanks!

1 ACCEPTED SOLUTION

Ankur Bawiskar
Tera Patron

Hi Kate,

So the planned start date should not be more than 7 days from now

You can use UI policy on change request table for this with condition as below:

find_real_file.png

 

find_real_file.pngscript: for execute if true

alert("Please select planned start date within 7 days from now");
g_form.clearValue('planned_start_date'); // use proper field name here

Mark Correct if this solves your issue and also mark Helpful if you find my response worthy based on the impact.
Thanks
Ankur

Regards,
Ankur
✨ Certified Technical Architect  ||  ✨ 10x ServiceNow MVP  ||  ✨ ServiceNow Community Leader

View solution in original post

10 REPLIES 10

Ankur Bawiskar
Tera Patron

Hi Kate,

So the planned start date should not be more than 7 days from now

You can use UI policy on change request table for this with condition as below:

find_real_file.png

 

find_real_file.pngscript: for execute if true

alert("Please select planned start date within 7 days from now");
g_form.clearValue('planned_start_date'); // use proper field name here

Mark Correct if this solves your issue and also mark Helpful if you find my response worthy based on the impact.
Thanks
Ankur

Regards,
Ankur
✨ Certified Technical Architect  ||  ✨ 10x ServiceNow MVP  ||  ✨ ServiceNow Community Leader

Thank you!

If you want Business Rule. 

before and insert,update checked

Condition : Planned start date changes or isnot empty 

script

var getPlannedDate = current.start_date;
var dc = new DurationCalculator();
dc.setSchedule('08fcd0830a0a0b2600079f56b1adb9ae'); // this is the sys_id of 8-5 weekday schedule in the instance.
dc.setTimeZone('GMT');
var dur = dc.calcScheduleDuration(gs.now(),getPlannedDate)/3600;
var res = dur.toString();
if(parseInt(res)>= 45){ // Check for  days
gs.addErrorMessage("Please select planned start date within 7 days from now");
current.setAbortAction(true);
}

Regards
Harish

How about if Planned End Date > Planned Start Date?

You have to play a little bit to fine-tune it, but something like below. Then only add your error message in the script.

find_real_file.png

If my answer helped you in any way, please then mark it as helpful.

Kind regards,
Mark

---