Project schedule is not behave like it supposed to

Yaron Rabinovi1
Tera Expert

Hi,

I have set a schedule for the project so that it will be from Sunday to Thursday (excluding Friday and Saturday) between the hours of 08:00 and 17:00

However, the project tasks do not consider the schedule and show dates that fall on Fridays and Saturdays.

What am I doing wrong?

YaronRabinovi1_0-1724060519321.pngYaronRabinovi1_1-1724060546420.pngYaronRabinovi1_2-1724060567533.png

 

2 REPLIES 2

Mark Manders
Mega Patron

How are you creating the tasks? Are you attaching the same schedule to the tasks? 


Please mark any helpful or correct solutions as such. That helps others find their solutions.
Mark

Yaron Rabinovi1
Tera Expert

I create the task through Project Work Space.

I defined the schedule in the project itself and did not assign tasks to it.
The tasks should inherit the schedule from the project.