Project schedule is not behave like it supposed to

Yaron Rabinovi1
Tera Expert

Hi,

I have set a schedule for the project so that it will be from Sunday to Thursday (excluding Friday and Saturday) between the hours of 08:00 and 17:00

However, the project tasks do not consider the schedule and show dates that fall on Fridays and Saturdays.

What am I doing wrong?

YaronRabinovi1_0-1724060519321.pngYaronRabinovi1_1-1724060546420.pngYaronRabinovi1_2-1724060567533.png

 

2 REPLIES 2

Mark Manders
Tera Patron

How are you creating the tasks? Are you attaching the same schedule to the tasks? 

Yaron Rabinovi1
Tera Expert

I create the task through Project Work Space.

I defined the schedule in the project itself and did not assign tasks to it.
The tasks should inherit the schedule from the project.