Requested Allocations are not creating in Resource Plan
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-17-2017 12:51 PM
Whenever a Resource plan is created, I am getting an error "Cannot create Requested Allocations as there are no working days in the schedule for the plan date range", and Requested allocations are not getting created.
When i reviewed, I found that the error is being generated from the script include "ResourcePlan".
Anyone could help me on this issue. Why I am getting this error?
Thanks in Advance
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎05-31-2018 05:11 AM
you ever figure this out?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-06-2018 09:24 AM
This is most likely that default schedule is missing. Go to Project Administration > Settings > Properties - Resource. See what is in the Default Schedule Name (Out-of-box it is Resource Management Schedule). Then go to System Scheduler > Schedules > Schedules. Make sure that you have the same name of the schedule there. If it is not there find another schedule you want to use or create a new schedule and set the name of it in Properties - Resource for the Default Schedule Name.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-07-2025 12:47 PM
It's there for me and correct. Also, only having this issue for one user and only in Prod. Only after a certain date.