I need help creating a Schedule job that creates a HR case twice a year, every 5th business day of May and November
2 REPLIES 2
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-09-2024 03:58 AM
Are there any (banking) Holidays in the first week of May or November where you are located? Or can we just assume on skipping the weekends? That would make it easier.
Please mark any helpful or correct solutions as such. That helps others find their solutions.
Mark
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-09-2024 04:11 AM
Yes there are bank holidays in the first week of both months