Table to manage budget

miyu
Tera Guru

Is there a table to manage the budget separately from the Expense Line?
I understand that the Expense Line table is a table to manage asset charges.

5 REPLIES 5

Sulabh Garg
Mega Sage

Hello

If the context is PPM, Then you can explore these tables

1) cost_plan

2) benefit_plan

3) resource_plan

Please Mark ✅ Correct/helpful, if applicable, Thanks!! 

Regards

Sulabh Garg

Please Mark ✅ Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg

Thank you.
Is it possible to check all users in the above 3 tables?
I checked with PDI, but could not find all tables.
Do I need to install a plugin?

Yes, Please Install 'PPM Standard' Plugin for the same.

Please Mark ✅ Correct/helpful, if applicable, Thanks!! 

Regards

Sulabh Garg

Please Mark ✅ Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg

Vinayak Belgaon
Mega Guru

Budget is managed in the Portfolio Target (project_funding) table.

You can see a related link on project and demand to create budget. 

 

Regards

Vinayak