Hi All,
Once the change is moved to Assess state, all the fields will be read only on the change form. But users are still be able to edit planned start and planned end dates from conflict calendar UI action button as shown below.
How to restrict that?
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
It’s a known issue in ServiceNow: even when Planned Start / Planned End are read only on the form or blocked by ACLs and Business Rules, users can still open the Conflict Calendar popup and edit them from there because the Change Request Calendar View doesn’t enforce those ACLs or BRs and allows editing despite write restrictions.....
If you found my response helpful, please mark it as ‘Accept as Solution’ and ‘Helpful’. This helps other community members find the right answer more easily and supports the community.
Kaushal Kumar Jha - ServiceNow Consultant - Lets connect on Linkedin: https://www.linkedin.com/in/kaushalkrjha/
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
Hi @nandini29
No, mate — no way. The reason is conflict. The schedule page is not a native form, and the code isn’t easily accessible to us. It’s better to log a case with ServiceNow.
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
It’s a known issue in ServiceNow: even when Planned Start / Planned End are read only on the form or blocked by ACLs and Business Rules, users can still open the Conflict Calendar popup and edit them from there because the Change Request Calendar View doesn’t enforce those ACLs or BRs and allows editing despite write restrictions.....
If you found my response helpful, please mark it as ‘Accept as Solution’ and ‘Helpful’. This helps other community members find the right answer more easily and supports the community.
Kaushal Kumar Jha - ServiceNow Consultant - Lets connect on Linkedin: https://www.linkedin.com/in/kaushalkrjha/
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
Hi @kaushal_snow Can we restrict this through UI Action? can we give roles in required roles tab so that we can restrict users from updating through conflict calendar?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hi @nandini29
This is expected behavior, although we can consider it a known issue or bug. You can log a case with ServiceNow to see if they can provide any input or feedback on it.
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
@Dr Atul G- LNG
I want to know is there any possiblity to restrict the ability to update the date/time in the calendar itself.