Release dates with only business days
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-12-2024 10:34 AM - edited 12-12-2024 11:26 AM
Hi all, I have configured a release template using the option timeline oriented and each phase has a different duration. My goal is to discard weekends and holydays from the planned end date.
Let' s say that I have a template of 21 business days.
Phase 1 - 1 business day
Phase 2 - 3 business days
Phase 3 - 4 business days
Phase 4 - 10 business days
Phase 5 -3 business days
And my planned Realease readiness target will be 2025-01-15
I would like that phases end date showed:
phase 1 end planned date 2024-12-16
phase 2 end planned date 2024-12-19
phase 3 end planned date 2024-12-26
phase 4 end planned date 2025-01-10
phase 5 end planned date 2025-01-15
it seems that even if I setup workdays calendar is not working automatically have I missed some configuration?
Thanks
- 357 Views

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-13-2024 05:22 AM
Hi, we currently do not honour weekends and holidays, this one is on our backlog. We are looking to prioritise it based on the demand for this feature.
Thanks,
Balaji