Release dates with only business days

Mara6
Tera Expert

Hi all, I have configured a release template using the option timeline oriented and each phase has a different duration. My goal is to discard weekends and holydays from the planned end date.

Let' s say that I have a template of 21 business days.

 

Phase 1 - 1 business day

Phase 2 - 3 business days

Phase 3 - 4 business days

Phase 4 - 10 business days

Phase 5 -3 business days

 

And my planned Realease readiness target will be 2025-01-15

I would like that phases end date showed:

phase 1 end planned date 2024-12-16

phase 2 end planned date 2024-12-19

phase 3 end planned date 2024-12-26

phase 4 end planned date 2025-01-10

phase 5 end planned date  2025-01-15

 

it seems that even if I setup workdays calendar is not working automatically have I missed some configuration?

Thanks

 

 

1 REPLY 1

Balaji39
ServiceNow Employee
ServiceNow Employee

Hi, we currently do not honour weekends and holidays, this one is on our backlog. We are looking to prioritise it based on the demand for this feature.

 

Thanks,

Balaji