Dispatcher Workspace task duration vizualisation

lars7
Tera Guru

Hi

 

My customer is asking about the possibilities of vizualising the various durations of a task in the dispatcher workspace calender view.

 

Right now, a task that have been worked on and paused on day 1, and then resumed on day 2, is not being vizualised on day 2 because estimated duration is not spanning into day 2. So, until the task is closed and completed, the task will continue to reside visually on day 1, which is arguably misrepresenting the reality of things.

 

Essentially what is asked for is this kind of vizualisation. Is it possible and if so, how?

lars7_0-1723625467694.png

 

1 REPLY 1

Mark Manders
Mega Patron

Simple answer: no, this is not possible (OOB).

But you could try to run a flow/scheduled job at the end of the day, looking for all non completed tasks that started on or before today and update the estimated duration to go into the next day.


Please mark any helpful or correct solutions as such. That helps others find their solutions.
Mark