07-21-2026 10:36 AM
Hi all,
Is there a matching dimension can ensure we comply with the working directive for an engineer to have a downtime of 11 hours after 8 hours continuous work?
I can see Last Assigned but this doesn't quite meet the requirement above. Has anyone built a custom matching dimension or have any suggestions on how to achieve this?
Thanks.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-21-2026 10:56 AM
Hey Chaz, is there an option to use agent schedules here. If work done for 8h, then agent off shift and should not receive work automatically since they are not available.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-21-2026 10:56 AM
Hey Chaz, is there an option to use agent schedules here. If work done for 8h, then agent off shift and should not receive work automatically since they are not available.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-23-2026 02:11 AM - edited 07-23-2026 02:11 AM
Excellent - that will work. I missed the simple and obvious solution. Thanks.