When the change type is normal in change request, show the popup message in freeze period

akila reddy
Tera Contributor

Hi  Everyone, i have a requirement on change request. There are freeze periods mentioned in the cmn_schedule_span table like start date and end date of the freeze period. So whenever the change request is raised with the type as "Normal" and the planned start and end dates fall under this freeze period then a section called justification should appear beside the worknotes and also a pop up message should come as 

"You are attempting to implement this change during a freeze period. Please provide justification in the Business Justification field on why this change must be implemented on this date.");
akilareddy_0-1727169077782.pngakilareddy_1-1727169140289.png

 

 
Please suggest me the solution for this.