Hello KP,
You can achieve this by setting "max_unit" attribute in the dictionary of Remaining Effort field.
1.Right click on duration field.
2.Goto configure dictionary.
3.Click advance ui action under related links.
4.Add max_unit=days in the Attribute field.
5.save the record.
Let me know if you have any question.
Hit Helpful or Correct on the impact of response.