We were not able to auto close our system when the associated change and sctask were closed out. Also Associated change was closed but the corresponding SCTASK didnt get auto close.
2 REPLIES 2
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-02-2026 04:04 AM
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-02-2026 04:08 AM
Out-of-the-box (OOTB), this only happens when an SC Task is closed, and the RITM and REQ are closed. It has no relation to Change tasks. If you want to build this relationship, you will need to implement your own logic.