Calculate conflict detection based on Planned start date and Planned end date

Samiksha2
Mega Sage

Hi All,

 

We are considering using the Blackout Calendar for change freezes, but we would only need to check the Planned Start Date and Planned End Date.

Is this possible?

 

Thanks,
Sam

3 REPLIES 3

Dr Atul G- LNG
Tera Patron

Yes but not recommended. Please check the conflict property

 

AGLearnNGrow_0-1717681856794.png

 

*************************************************************************************************************
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/dratulgrover [ Connect for 1-1 Session]

****************************************************************************************************************

Hi @Dr Atul G- LNG ,

If we unchecked that, then how it work?

 

Thanks,
Sam

Hi @Samiksha2 

 

OOTB this property take 3 parameters and if you untick, it will not consider these 3 parameter for conflict.

*************************************************************************************************************
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/dratulgrover [ Connect for 1-1 Session]

****************************************************************************************************************