Change "Configuration item/Affected CIs, Planned start date and Planned end date are required to run conflict detection"

selenasmith
Kilo Contributor

Where is the error message "Configuration item/Affected CIs, Planned start date and Planned end date are required to run conflict detection located"?   I have a request from the product owner to change the message and I can't locate it in our system.


Thanks,

Selena Smith

1 ACCEPTED SOLUTION

Michael Fry1
Kilo Patron

UI Macro: change_request_conflict_progress


There are 2 warningMessage that you could update.


View solution in original post

2 REPLIES 2

Michael Fry1
Kilo Patron

UI Macro: change_request_conflict_progress


There are 2 warningMessage that you could update.


Thank you!   That's exactly what I needed.