Hello. Looking for some advice on searching on changes to ensure they were implemented within the window. Right now I am manually looking at closed changes and comparing planned and actual times. Is there way to run a report that can determine if a change was done  outside of the approved change window? 

2 ACCEPTED SOLUTIONS

Ahmmed Ali
Giga Sage
Giga Sage

You can configure one report on change request table with condition as below

AhmmedAli_0-1680713469556.png

 

If I could help you with your Query then, please hit the Thumb Icon and mark my answer as Correct!!

Thank you,
Ali

View solution in original post

I had to make a small adjustment but your advice was spot on and is working as expected. Thank you very much.

View solution in original post

3 REPLIES 3

Ahmmed Ali
Giga Sage
Giga Sage

You can configure one report on change request table with condition as below

AhmmedAli_0-1680713469556.png

 

If I could help you with your Query then, please hit the Thumb Icon and mark my answer as Correct!!

Thank you,
Ali

I had to make a small adjustment but your advice was spot on and is working as expected. Thank you very much.

Thank you again for your response. I have one other question. What happens to a change that is on hold once it reaches its planned end date? Would it be considered past due? Also, how long can a change stay on hold?