Maintenance and blackout schedules should be defined and available in the system so that change requesters understand when a change can be implemented and when they should not be implemented.

1. Create a maintenance schedule named: "Data Center - Maintenance Weekend Schedule".

a) Should be applied to all "Network", "Unix Server", and "Linux Server" CI classes.

b) Create a schedule entry for all day, every Monday (repeating weekly) until the end of the year as part of this schedule.

2. Create a blackout schedule named: "Monthly Freeze/Blackout Period".

a) Should be applied to all CI classes.

b) Create a schedule entry for every 3rd Thursday of each month (repeating monthly), until the end of the year as part of this blackout schedule.

 

Can someone point out what's wrong here???

 

find_real_file.png

find_real_file.pngfind_real_file.pngfind_real_file.png

21 REPLIES 21

tonyservian
Tera Contributor

 

 

 

 

I'm doing this lab and the answer is:

"Task Result: Failed

Please validate the Data Center - Maintenance Weekend Schedule maintenance schedule was created correctly. Have you included all three classes required?"

And the steps I have taken are the ones I attach in images.
Can someone help me please? 

 

hardcopy1.jpg

hardcopy2.jpg

  

 

Please also attach the Question for this. It might not be the same question.

Your configuration appears to be correct but it seems you created the maintenance schedule on a blackout schedule menuschedules.png

amol_joshi
Tera Contributor

Maintenance and blackout schedules should be defined and available in the system so that change requesters understand when a change can be implemented and when they should not be implemented.

1. Create a maintenance schedule named: "Data Center - Maintenance Weekend Schedule".

  a) Should be applied to all "Network", "Unix Server", and "Linux Server" CI classes.

  b) Create a schedule entry for all day, every Monday (repeating weekly) until the end of the year as part of this schedule.

2. Create a blackout schedule named: "Monthly Freeze/Blackout Period".

  a) Should be applied to all CI classes.

  b) Create a schedule entry for every 3rd Thursday of each month (repeating monthly), until the end of the year as part of this blackout schedule.

Hint: Validate the Source field is set to the proper value!

amol_joshi
Tera Contributor

I created blackout schedule under the maintenance schedule. That was the biggest problem.