I am working on a flow design. There is a date time field on the RITM.

I have created a task in the flow design itself.

I have to trigger the above task 45 days before of that date time field value.

For example: that date time field is 'X' and the value of this 'X' field is 1st Dec.

So as per the requirement, that task that I have created in the flow design itself that will be generated on 16th Oct.

I am not able to achieve it.

Can anyone please help me out ASAP as it is urgent.

 

Thanks&Regards,

Abhisek Chattaraj.

4 REPLIES 4

AnveshKumar M
Tera Sage
Tera Sage

Hi @abhisek  ,

 

Can you try using relative time like the one below in the screenshot based on your date time field.

 

1080 Hours (45 days x 24 hours) :: Before :: Target Date

 

AnveshKumarM_0-1695365588396.png

 

See the test run screenshot below:

AnveshKumarM_1-1695366018763.png

 

AnveshKumarM_0-1695365994898.png

 

 

Please mark my answer helpful and accept as solution if helped you 👍✔️

 

Thanks,
Anvesh

Hi Avnesh,

 

This is not working as it is picking up any date 45 days in past as compared to that date time field value.

 

Thanks&Regards,

Abhisek Chattaraj. 

Hi @abhisek  

What is your requirement if the date falls in past date? I can help you on that.

 

Thanks,
Anvesh

Hi Avnesh,

 

That task should be triggered exactly 45 days back as compared to that date time filed value.

 

Thanks&Regards,

Abhisek Chattaraj.