How to created schedule for 2 business weeks

lucky24
Tera Contributor

Hi Team,

I have created one SLA definition in which I have to set SLA duration "2 business week".

How can we create schedule  for 2 business week?

 

2 REPLIES 2

AndersBGS
Tera Patron
Tera Patron

Hi @lucky24 ,

 

Utilize the schedule within the SLA definition and utilize a schedule entry like the one below OOTB:

AndersBGS_0-1705480077062.png

Remember to calculate the SLA so a 24 hours across 8 hours working day = 3 days. 

 

If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

best regards

Anders 

 

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

JaeggerLegane
Kilo Sage

Hello Lucky,

1. Set the field "Duration" on 10 days:

JaeggerLegane_0-1705480248002.png

2. Create a schedule or update an existing schedule and make sure it only counts weekdays.

Example:

JaeggerLegane_1-1705480357182.png

JaeggerLegane_2-1705480399092.png

 

 

--------------------------------------------------------------------------------
If my post helped you, please click the accept solution button and hit the thumbs up! Thank you!