At the moment projects "planned efforts" calculate 1day = 24 hours. This really hard for project managers and looking to change 8hr date. Is there any way to change "planned effort" same as business hours 1day=8hr?

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-09-2014 05:39 AM
I think all you need to do here is apply a schedule that uses an 8 hour day. Have you already tried this?
ben
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-10-2014 08:51 PM
Thanks Ben. Since "Planned effort" is manually entered date/time field schedule can not be used in here.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-09-2014 04:54 PM
Sounds like you are trying to change the behavior of these duration fields, I don't think this is possible, but I will let others chime in.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-09-2014 05:59 PM
CHRISTUS Health customized their PPM to use the 8 hr day several years ago. Dave Knight was a big help since changing the duration isn't an easy process.