Project: Planned effort change from 24hr to 8hr

attanhes
Tera Guru

At the moment projects "planned efforts" calculate 1day = 24 hours. This really hard for project managers and looking to change 8hr date. Is there any way to change "planned effort" same as business hours 1day=8hr?

6 REPLIES 6

tbibarrett
Kilo Explorer

HS_ATT - I attended the North Texas SN User Group yesterday and I was asking the question regarding this subject.   Our company is behind in the upgrade process, so we're still on Berlin.   My understanding is that there have been updates to the PPM, which may include more options for the duration calc.   I'd contact your SN account manager and let them explore the options.


ettawilson
Mega Sage

Hello,



Starting in Dublin, there's a schedule called Project Management Schedule that is a standard 8 hour per day schedule.   Here's a link on the wiki for the additional enhancements. http://wiki.servicenow.com/index.php?title=Project_Management#Enhancements



If you want to see it in action, you can use the public sandbox to test it out. http://wiki.servicenow.com/index.php?title=ServiceNow_Public_Sandbox



Etta