what is the lead time the change is considering to reflect as Low risk.
(Because i have noticed, when the change submitted time nearer to planned start window then risk gets changed from Low to High) , hence need to know this dependency as well.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-03-2025 06:06 AM
Hi @PadminiY
Out-of-the-box, it is set to 3 days, meaning a change raised 3 days before the planned start is considered low risk due to the lead time.
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-03-2025 06:09 AM
Hi @PadminiY ,
You can Navigate to All > Change > Administration > Risk Conditions, open the required Risk condition to validate what is the condition used to display the risk as Low/High Risk.
For example :
Here, look at the condition which is considering the "planned start date".